Nine day closure of South East London rail lines

Watch more of our videos on Shots! 
and live on Freeview channel 276
Visit Shots! now
Network Rail has announced the nine-day closure of South East London lines to complete ‘critical signalling work.’

The railway through Hither Green, in South East London, will be closed for nine days from Saturday July 25 to Sunday August 2 for signalling upgrades through the area.

The work is the commissioning of new signalling equipment and the transfer of control from London Bridge Area Signalling Centre to Three Bridges Rail Operating Centre. It will mark the end for the old signalling location, which has been in continuous use since 1975.

Hide Ad
Hide Ad

The work is a key part of Network Rail’s £250m investment to improve signalling and track reliability through the busy Lewisham area of South East London.

Nine day closure of South East London rail lines SUS-200522-152703001Nine day closure of South East London rail lines SUS-200522-152703001
Nine day closure of South East London rail lines SUS-200522-152703001

Network Rail says the 1970s signalling system, which controls the movement of trains on the Bromley North, Sidcup branches and main line through Hither Green, is being completely replaced with a modern, more reliable system.

Buses will replace trains on affected routes for the nine days, with services resuming on Monday August 3

Extra buses will be laid on to make sure social distancing can be achieved on the replacement services. Tickets will be accepted on alternative routes and Transport for London services, which will also be increased to ensure passengers travelling can maintain a 2m distance.

Hide Ad
Hide Ad

While extra capacity will be laid on, only critical passengers and those who absolutely must travel are advised to.

Network Rail route director Fiona Taylor said: “This work is so important for delivering a reliable railway for the many passengers who travel through this area. “The signalling system is very old and in urgent need of upgrade.

“We wanted to get this work done over Easter but because technicians can’t work closely together for long periods, it is going to take double the amount of time it would normally take to finish the job.

“We have taken the decision to complete the work in the summer holidays because we wanted to give those passengers who are still travelling, many of them critical workers, enough time to plan ahead.